Weekly Update

Setting forms and pier caps on interior of the building. 
Elevator shaft, completely formed, rebar in and ready for concrete. Pump truck arrived to pour grade beams. The parking lot, islands and light pole base locations have been marked. The manhole has also been connected and the water meter vault has arrived. 